Search & Filter
Simulation Data
Drag & Drop Simulation Files
Support for OpenDSS, GridLAB-D, and PowerFactory exports (.csv, .xml, .json)
Sample Simulations
| Name | Type | Description | Action |
|---|---|---|---|
| IEEE 13-Node Test Feeder | Voltage Profile | Standard test case with voltage violations | |
| PV Integration Study | Impact Analysis | High penetration PV with voltage rise issues | |
| Urban Distribution Network | Load Flow | Dense urban network with capacity constraints |
Simulation Parameters
| Parameter | Value | Status |
|---|---|---|
|
Base Voltage
i
The nominal voltage level at which the distribution system operates.
|
12.47 kV
|
OK |
|
Power Factor
i
Ratio of real power to apparent power. Indicates efficiency of power utilization.
|
0.92
|
Warning |
|
Voltage Drop
i
Percentage reduction in voltage from substation to end of feeder.
|
4.8%
|
Warning |
|
Peak Load
i
Maximum power demand on the feeder, measured in MVA.
|
3.2 MVA
|
OK |
|
Line Losses
i
Power lost as heat in conductors due to current flow, measured in kW.
|
87 kW
|
OK |
Distribution Network Visualization
Voltage Profile
Live Events
AI Interpretation
Analyzing simulation data...
Voltage Profile Analysis
The simulation shows voltage drops exceeding 4% on the extreme end of the feeder. This is within ANSI C84.1 Range A limits but approaching Range B at peak load conditions. Consider implementing voltage regulation at node N7.
Power Factor Improvement
Power factor of 0.92 indicates potential for improvement. Installing 450 kVAR of capacitive compensation would improve power factor to 0.98 and reduce losses by approximately 12%.
DER Integration Impact
The current network can accommodate up to 1.5 MW of additional distributed generation without voltage violations, primarily at nodes N4, N9, and N12.
DER Integration Analysis
Existing DERs
| Location | Type | Size | Action |
|---|---|---|---|
| N9 | Solar PV | 200 kW | |
| N12 | Solar PV | 350 kW |
Hosting Capacity Analysis
Recommended Actions
Short-term Recommendations
1. Adjust LTC tap position at substation from 1.025 to 1.0375 pu
2. Verify proper operation of capacitor bank at node N8
3. Check connection impedance at node N11 which shows abnormal values
Long-term Planning
1. Install 450 kVAR switched capacitor bank at node N7
2. Consider voltage regulator for lateral branch to nodes N9-N13
3. Reinforce conductor on main feeder segment S4-S5 to reduce voltage drop